Thailand weighs added capacity at Laem Chabang port

Thailand is considering further capacity options for Laem Chabang as foreign trade grows and regional supply chains are reshaped. The port’s ongoing third-phase project targets annual container capacity of 18 million TEU.

Text

Thailand has put additional capacity options for Laem Chabang, the country’s largest deep-sea port, on its agenda amid rising foreign trade and the restructuring of regional supply chains. Operated by the Port Authority of Thailand, the port is a major maritime gateway for export-oriented industries including automotive, electronics and petrochemicals.

Laem Chabang is already being expanded under its third-phase development programme. Information released by Thailand’s official investment and development bodies shows that the principal target is to raise annual container-handling capacity from 11 million TEU to 18 million TEU. The plan also aims to increase vehicle-handling capacity from 2 million to 3 million units a year and expand the share of rail transport.

According to project information published by the Eastern Economic Corridor Office, the development is located in Si Racha district of Chon Buri province and is owned by the Port Authority of Thailand. The F1 and F2 terminals are planned with capacity of 4 million TEU a year, while the E1 and E2 terminals are planned for 3 million TEU a year. The multipurpose E0 terminal is also included in the project.

The official project page lists total investment at 110,924 million baht. Of that amount, 49,138 million baht is expected to be provided by the Port Authority of Thailand and 61,786 million baht by the private sector. GPC International Terminal Ltd. is named as the private partner for the F terminal, with the contract signing date listed as 25 November 2021.

The expansion extends beyond added berths and terminal capacity. It includes automated container-management systems, development under a “green port” approach and a higher share of cargo moved by rail. The Eastern Economic Corridor Office aims to raise rail’s share of total freight transport from 7% to 30%. The Thailand Board of Investment says the combined capacity of all three phases is targeted to reach 18 million TEU once the third phase is completed.

The current schedule lists the opening of the F1 terminal in 2027 and the F2 terminal in 2031. Firm opening dates for the E0, E1 and E2 terminals are listed as “to be determined.” No new capacity target, timetable or investment amount for an additional expansion has been officially announced.