Irrigation projects involving Chinese companies in Uzbekistan have been delayed by disagreements over construction costs, Water Resources Minister Shavkat Khamraev said on 11 November at a Government Hour session in the Legislative Chamber of the Oliy Majlis.
Imomnazar Tursunov, a deputy from the People’s Democratic Party of Uzbekistan, said work had still not begun on several investment projects planned for 2026. He raised the reconstruction of irrigation infrastructure in the Surkhandarya, Kashkadarya, Bukhara and Namangan regions. Funding of $130 million was envisaged with the participation of the Export-Import Bank of China, while the table presented for the projects showed that not a single sum had been spent, he said.
Khamraev said the ministry had initially planned to bring in CITIC and CAMC. The companies were expected to start construction with their own funds and later recover the costs from China’s concessional loans. Instead, they submitted proposals that were not 10% or 20% above expectations but more than twice as high. The ministry spent more than a year seeking acceptable terms, but the talks did not produce an agreement.
The government then approached the Chinese side to seek financing through the Export-Import Bank of China under the established procedure. The bank’s review of a project, including expert assessment, takes about six months, Khamraev said, while selecting a contractor from several companies took another year. CITIC won a tender involving three companies but sought a price 20% higher than initially planned. After the ministry failed to agree a reduction, it began negotiations with Sinohydro. A further meeting with the company’s representatives took place on the morning of 11 November before the parliamentary session.
The ministry will not accept an inflated price simply to start construction faster, Khamraev said. “If we agree to a high cost in order to complete the work more quickly, the funds will still have to be repaid from the budget. That is why the matter has been suspended for now,” he explained. The programme will take at least two years, while project documentation has already been prepared and passed expert review. Canal lining is planned for 2027–2028.
The document set the preliminary total cost of two projects at $220 million. It allocated $160 million for irrigation infrastructure reconstruction in the Bukhara, Namangan and Surkhandarya regions and $60 million for Kashkadarya. For the Kashkadarya project, 120 billion soums from the local budget were envisaged in 2025 for a 15% advance payment. The ministry said it intended to complete the work to the required standard and within the planned financing.