School No. 42 in Bukhara’s Furkat mahalla has been declared unfit for further use after part of a ceiling collapsed in October. The incident occurred at about 11:00 on 15 October in the assembly hall on the third floor, and no one was injured. The building was constructed in 1958 for 800 pupils, but it now serves more than 1,300 children.
Inspectors later identified settlement and deformation of structures in other parts of the building. A construction inspection report dated 9 November said the wooden roof and floor structures had deteriorated, rotted and become deformed. The report also noted vibrations in floors and beams in some classrooms, warned of a risk of another collapse and recommended stopping use of the building.
Since 16 November, younger pupils have been attending classes in premises belonging to a law college. Older pupils have been placed at School No. 44, about 500–600 metres from the former building, where lessons are being held in two shifts. School principal Halima Nurullayeva said the teaching process had not been interrupted.
There are differing accounts of when the inspection was initiated. An official document states that the construction inspectorate began its assessment on the basis of a request from the city department of preschool and school education dated 24 September. The school principal, however, said the request was sent after the ceiling collapse on 15 October. The regional education department said technical assessments of building conditions fall under the construction inspectorate’s authority and that schools cannot obtain such assessments annually because the service is paid.
At an off-site meeting in Bukhara region on 3 March, authorities were instructed to build an additional 540-place block on the school grounds. Funding was allocated for preparing the design and cost-estimate documentation, which is now being developed. Following the incident, the regional administration is also considering increasing the building’s capacity to 880 pupils.
Social media reports also said pupils had been involved in moving desks and furniture. The regional education department said no repair work was under way on the school grounds and that equipment was being moved to safe premises. According to the department, technical staff and parents who came voluntarily took part on Sunday, 15 November. It was also reported that older pupils and graduates helped carry lighter items. The State Labour Inspectorate said it had taken the matter under review and was examining the claims received.